June 12, 1969

Mr, Addy Chan

Room 901 City Hall
68 Mitchell St., S.W,
Atlanta, Georgia

Re: City Hall Atmex # 3, Atlanta, Ga,

Dear Sir,

In regards to our completion date of June
20th we are asking for this date be extended to
the 27th, The reason for this request is due to
the problem of poor soil ccndition and rain that
has hindered the completion of out side stair well,
To meet this date of the 27th as we stated over
the phone we are asking for a preliminary inspection
Friday, June 13th and our final inspection Friday
June ?0th, This will give us a week to finish the
work where the building will be acceptable June 27th,

This will assure you of a good job, and we feel
the City will be better satisfied, and this will give
us adequate time to caught up the necessary items
on punch list to make the job complete,

We trust this is acceptable and agreeable,