February 11, 1969

1969 MODEL CITY PROJECTS
A.
1969 Rehabilitation Project R-1
Replace 5 old style fire hydrants with 5-4 1/4" fire hydrants
@ approx.
$1,085.45
1.
B.
1969 Rehabilitation Project R-2
1.
2.
~
3.
4.
5.
C.
Replace 4 old style fire hydrants with 4-4 1/4" fire hydrants
@ approx.
$
868.36
Install 800' - 8 11 water main in Primrose St. from Atlanta Ave. to South Ave.
@ approx.
$ 6,656.00
Install 800' - 811 water main in Connally St. from Atlanta Ave. to South Ave.
@ approx.
$ 6,656.00
Install 800' - 8 11 water main in Greenfield St. from Vanira Ave. to ·ormand St.
@ approx.
$ 6,656.00
Install 800' - 8 11 water main in Martin St. from Vanira Ave. to Ormand St.
@ approx.
$ 6,656.00
1969 Rehabilitation Project R-3
1.
2.
Replace 8 old style fire hydrants with 8 4 1/4" fire hydrants
@ approx.
$1,736.72
Install 1000' - 8 11 water main in Rosedale Ave. from Home St. to Delmar Ave.
@ approx.
$ 8,320.00
Total Estimated Cost for Rehabilitating Areas
D.
1969 Clearance Project C-1
1.
2.
E.
2.
Plug 811 main in Richardson St. from Wirt'sor St. :to Cooper St.
128.00
@ approx.
$
11
Plug 6 main in Cooper St. from Richardson St. to Fulton St.
@ approx.
128.00
$
1969 Clearance Pr oj ect C- 3
1.
G.
Plug 811 main in Berrele St. from Coleman St. to McDaniel St.
@ approx.
$
128.00
Plug 611 main in Middle St. from Coleman St. to McDanie1-:.st.
@ approx.
$
128.00
1969 Clearance Project C-2
1.
F.
. $ 38,634.53
Plug 6" main i n Cherokee St. from Martin St. to Connally St .
@ a pprox.
$
128 . 00
1969 Clearance Project C-4
-
no work
Total Estimated Cost for Clearance Areas
$
640.00
Graad Total
$
39,274.53