Weekly Construction Report RE: STADIUM

For Week Ending October 13, 1964.

ENCLOSURES :

WEATHER:

CPM SCHEDULE:

(8) Photographs each to: Mayor Allen
Mr. Montgomery
Mr. Lane
Heery & Heery
FABRaP

Wednesday October 7 Clear, 48° AM; Clear 650 PM
Thursday October 8 Clear, 46° AM: Clear 64° PM

Friday October 9 Clear, 50° AM; Clear 68° PM
Saturday October 10 Fair, 48° AM; fair, 57° PM
Sunday October 11 fair, 48° AM; fair, 66° PM
Monday October 12 Clear, 47° AM; clear 66° PM

Tuesday October 13 Partly cloudy, 54-1/2° AM
ji partly cloudy, 72° PM

182 days elapsed; 183 days remain.

This is the half-way point, and although we have

no CPM printout this week, progress seems satisfactory.
The General Contractor advised us today that Ingalis

is going on a three shift day and six day week until
further notice to insure performance of their schedule.












HEERY AND HEERY + FINCH, ALEXANDER, BARNES, ROTHSCHILD AND PASCHAL

Page 2
ACTIVITY:

THOMPSON & STREET - (General Contractor)

Poured ramp wall 64-57/E at service level. Graded fill at
service level. Poured main concourse topping. Formed West
wall at pedestrian tunnel (partial). Poured lower level
seating risers 37-39, 32-34, 44-45, 47-48, 64-67,

68-76. (all partial). Setting precast seating units at
main concourse 45-54. Setting door frames at service level.
Poured precast units.

CECO
Removed ramp forms 21-26 service level.

WESTERN - (Waterproofing)
Waterproofed main concourse 36-39 (partial). Completed
waterproofing lower level. Waterproofed West end of
Pedestrian tunnel. Placed sealant in construction and
expansion joints at lower level seating risers.

DIXIE
Erected masonry 43-57/C-E at service level.

ROBERTSON

Installed metal deck at upper concourse 46-49, and at
Club Deck to 56.

INGALLS
Unloaded steel, erected upper seating bent at 45. Erected
ramp beams 41-43. Welded to 68. Columns to 77 and beams
to 75. Erected upper concourse framing 41-43.

GULF

Set reinforcing steel on metal deck at ramp slabs. Set
reinforcing steel in North wall service tunnel (partial).

Roughed in 6-7/C-D, 65-67/C-D, 48-50/C-D, 31-33/C-D at
service level. Roughed in at Club Deck.




HEERY AND HEERY + FINCH, ALEXANDER, BARNES, ROTHSCHILD AND PASCHAL

Page 3

ACTIVITY (cont.)
CLEVELAND

Conduit etc., in masonry walls and Club Deck, roughed
in 17-21/A-B at service level.

NORTH BROTHERS

Installing pipe insulation at service level.

AMERICAN SEATING

Drilling holes in Lower level seating risers.

HEERY & HEERY + FINCH ALEXANDER BARNES ROTHSCHILD & PASCHAL

F. William Mitchell
Project Manager

CC: Mayor Allen
Mr. Lane
Mr. Scarborough
Project Representative
FABRaP
H&H